40 MainEco Heat 7215845 - 01 (08/14)
7 Commissioning
7 Commissioning
7.1 General
1. Reference should be made to BS:EN 12828 & 14336 when
commissioning the boiler.
2. At the time of commissioning, complete all relevant sections of
the Benchmark Checklist at the rear of this publications.
3. Turn the gas supply on and purge according to in GB BS 6891
and in IE I.S. 813 “Domestic Gas Installations”.
The combustion for this appliance has been checked,
adjusted and preset at the factory for operation on the
gas type specified on the appliance data plate.
7.2 Checklist before Commissioning
7.2.1 Preliminary Electrical Checks
1. Prior to commissioning preliminary electrical system checks
should be carried out.
2. These should be performed using a suitable meter, and
include checks for Earth Continuity, Resistance to Earth, Short
Circuit and Polarity.
7.2.2 Checks
Check that the boiler has been installed in accordance with
these instructions.
Check the integrity of the flue system and the flue seals.
Check the integrity of the boiler combustion circuit and the
relevant seals.
Check the integrity of all gas and water joints.
7.3 Commissioning Procedure
1. Open the main gas supply.
2. Open the gas cock on the boiler.
3. Set the controls (thermostats, control system) so that they
request heat to turn the boiler on.
4. The boiler incorporates an automatic air vent. As supplied
this is in the open position to allow venting of the system.
CAUTION
On first firing the boiler, an odour may be present for
a short period.