10.0 Commissioning
© Baxi Heating UK Ltd 2014
10.2 Checking the Combustion - ‘Chimney Sweep’
Function
1. To set the boiler to operate at MAXIMUM and MINIMUM,
press & together and hold for at least 6
seconds. ‘On’ will be displayed briefly, followed by ‘304’ then
the boiler output expressed as percentage i.e. ‘100’.
2. Press until ‘00’ is displayed, indicating minimum
input.
3. To exit the function press & together for 6
seconds.
4. The combustion (CO level and CO/CO2 ration) must be
measured and recorded at MAXIMUM DHW input and
MINIMUM input.
5. Follow the flow chart on the next page to comply with the
requirement to check combustion on commissioning.
6. The system MUST be cold to ensure the boiler is operating
under full demand
Fig. 36a
Plug
Analyser Probe
Flue Sampling
Point
Seitenansicht 0
1 2 3 4 5 6 ... 25 26

Inhaltsverzeichnis

Seite 1 - 10.0 Commissioning

2710.0 Commissioning© Baxi Heating UK Ltd 201410.2 Checking the Combustion - ‘Chimney Sweep’ Function1. To set the boiler to operate at MAXIMUM and MI

Seite 2

3613.0 Changing Components© Baxi Heating UK Ltd 2014Socket HeadedScrewPump HeadPump BodyAutomatic AirVentFig. 53Fig. 54Electrical SupplyPlugPump FlowP

Seite 3

3713.0 Changing Components© Baxi Heating UK Ltd 201413.13 Safety Pressure Relief Valve (Fig. 55)1. Close the flow and return isolation taps and drain

Seite 4 - To change the information

3813.0 Changing Components© Baxi Heating UK Ltd 201413.15 P.C.B. & R.D.S. (Removable Data Stick) (Fig. 58)NOTE: Both P.C.B. and R.D.S. are availab

Seite 5 - 12.0 Servicing

3913.0 Changing Components© Baxi Heating UK Ltd 201413.16 Gas Valve (Fig. 59)IMPORTANT: After replacing the valve the CO2must bechecked and adjusted a

Seite 6

40© Baxi Heating UK Ltd 2014Fig. 61PlugAnalyser Probe14.0 Combustion & Calibration14.1 Checking the Combustion1. Combustion should be:-Natural Gas

Seite 7

4115.0 Electrical© Baxi Heating UK Ltd 201415.1 Illustrated Wiring DiagramX23 X37 X36X22 X20 X24X10X11X12X13X1X2Flue SensorHeatingReturnSensorHeatingF

Seite 8

4216.0 Short Parts List© Baxi Heating UK Ltd 2014Short Parts ListKey Description ManufacturersNo.No. Part No.A Fan 720768101B Burner (12/15/18/24/28)

Seite 9

4317.0 Fault Finding© Baxi Heating UK Ltd 201417.1 Initial Fault Finding Checks1. Check that gas, water and electrical supplies are availableat the bo

Seite 10 - 13.0 Changing Components

4417.0 Fault Finding© Baxi Heating UK Ltd 2014Refer to “Illustrated Wiring Diagram” for position of terminals and componentsCentral Heating - Follow o

Seite 11

4517.0 Fault Finding© Baxi Heating UK Ltd 2014Fault Finding Solutions SectionsIs there 230V at:Main terminals L and N Check electrical supply1.NOMain

Seite 12

2810.0 Commissioning© Baxi Heating UK Ltd 2014Set Boiler to Maximum Rate(see 10.2.1)Allow the combustion to stabilise. Do not insert probe toavoid ‘fl

Seite 13

4617.0 Fault Finding© Baxi Heating UK Ltd 2014Replace PCBCheck and correct if necessary1. Ignition electrode and lead2. Electrode connection3. Spark g

Seite 14 - 14.3 Adjusting the CO

18.0 32 kW Model Supplement© Baxi Heating UK Ltd 2014Outercase DimensionsCasing Height - 763mmOverall Height Inc Flue Elbow - 923mmCasing Width - 450m

Seite 15 - © Baxi Heating UK Ltd 2014

4818.0 32 kW Model Supplement© Baxi Heating UK Ltd 2014360° Orientation Flue Ø 100mmDCBAEGFAt least 1.5°HJBoilerSideBoilerSideHeatingFlow(22mm)GasInle

Seite 16 - 16.0 Short Parts List

4918.0 32 kW Model Supplement© Baxi Heating UK Ltd 20141NOTE: The main difference between Megaflo 32 kW andother models in the range is the position o

Seite 17 - ‘Service Due’ Message

*All installations in England and Wales must be to Local Authority Building Control (LABC) either directly or through aCompetent Persons Scheme. A Bui

Seite 18 - 17.0 Fault Finding

www.centralheating.co.ukIt is recommended that your heating system is serviced regularly and that the appropriate Service Interval Record is completed

Seite 19

© Baxi Heating UK Ltd 2014BAXI A Trading Division of Baxi Heating UK Ltd (3879156)Brooks House, Coventry Road, Warwick. CV34 4LLAfter Sales Service 08

Seite 20 - Electrode Position

2910.0 Commissioning© Baxi Heating UK Ltd 2014Fig. 37Fig. 38Inlet Gas Pressure Test PointDO NOT check gas pressure here1. It may be necessary to adjus

Seite 21

30© Baxi Heating UK Ltd 2014Fig. 39Facia PanelCase Front Panel11.0 Completion & System Draining11.1 Completion1. Replace the case front panel, and

Seite 22 - 130mm 130mm 95 mm45 mm

3112.0 Servicing© Baxi Heating UK Ltd 201412.1 Annual Servicing1. For reasons of safety and economy, it is recommended thatthe boiler is serviced annu

Seite 23 - 18.0 32 kW Model Supplement

3212.0 Servicing© Baxi Heating UK Ltd 201412.2 Annual Servicing Inspection (Cont)5. Remove the clip securing the gas feed pipe to the air/gasventuri.

Seite 24

3313.0 Changing Components© Baxi Heating UK Ltd 2014IMPORTANT: When changing components ensure thatboth the gas and electrical supplies to the boiler

Seite 25 - SERVICE RECORD

3413.0 Changing Components© Baxi Heating UK Ltd 201413.4 Burner (Fig. 47) 1. Remove the clip securing the gas feed pipe to the air/gasventuri and disc

Seite 26 - Website www.baxi.co.uk

3513.0 Changing Components© Baxi Heating UK Ltd 201413.6 Flue Sensor (Fig. 49)1. For ease of access on 12 - 28 models remove theExpansion Vessel as de